Project Title: GMU President's Park Phase 2B

Project Location: Virginia

Project type: complete

GMU President’s Park Phase 2B

GMU President’s Park Phase 2B
GMU President’s Park Phase 2B
GMU President’s Park Phase 2B
GMU President’s Park Phase 2B
GMU President’s Park Phase 2B
GMU President’s Park Phase 2B
GMU President’s Park Phase 2B GMU President’s Park Phase 2B GMU President’s Park Phase 2B GMU President’s Park Phase 2B GMU President’s Park Phase 2B GMU President’s Park Phase 2B

This fast-paced project was completed over the summer of 2010. Starting on May 17 (the day after the students left for their summer break) DCG removed all furniture, roofing, doors, carpet, ceilings, air conditioning/heating equipment, electrical panels, lights, and wiring. By August 1, we had replaced all of these systems, added a completely new sprinkler system and were starting up the systems. By August 10th, the dorms were ready for students to move back in!

About Us Our Portfolio

Our team is always available to discuss your plans and ideas. Reach out to us today by going to our contact page or calling us at 540-428-3612.